Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Free Exam Questions

AACE-PSP Exam Questions & Answers

Planning & Scheduling Professional (PSP) Exam  •  AACE International

216 Questions Updated Sep 2026 99% Pass Rate
Get Full Access

100% money-back guarantee

Sample AACE-PSP Questions

Practice with real exam-style questions, each with the verified correct answer and explanation.

Q1 MultipleChoice

As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?

Correct Answer: A
Q2 MultipleChoice

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

Correct Answer: A
Explanation:

An earned value management (EVM) system can base its calculations on labor hours or monetary values, depending on the nature of the project. Both methods are valid for tracking performance and forecasting outcomes.

Option B (direct or indirect cost) does not align with EVM's focus on performance metrics.

Option C confuses timeframes with budgeting principles.

Option D (linear feet or dollars) applies to physical progress tracking but not directly to EVM systems.

This is consistent with EVM principles as outlined in project control methodologies within the PSP materials.

Q3 MultipleChoice

How could the structural steel drawing delay have been prevented?

Correct Answer: B
Explanation:

Preventing Structural Steel Delays:

Incorporating realistic timeframes for shop drawing review and resubmittals in the baseline schedule prevents design-related delays.

Evaluation of Other Options:

A: Adding time buffers does not address the root cause.

C: Concurrent review may create confusion and errors.

D: Switching to post-tensioned concrete is a significant design change, not a practical solution for a scheduling issue.

Verification with PSP Guidelines: Adequate review time aligns with PSP scheduling best practices (Ref: PSP Study Guide, Chapter 2B: Schedule Development and Baseline Creation).

Q4 MultipleChoice

Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?

Correct Answer: C
Q5 MultipleChoice

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Correct Answer: D
Explanation:

Cost for 2000 Series Activities:

Activity 2001: $150,000.

Activity 2002: $25,000.

Activity 2003: $18,000.

Activity 2004: $96,000.

Total: 150,000+25,000+18,000+96,000=289,000150,000 + 25,000 + 18,000 + 96,000 = 289,000150,000+25,000+18,000+96,000=289,000.

Total Project Cost:

Total cost: $7,308,000 (sum of all activities in 'normal' schedule).

Percentage Contribution:

289,0007,308,0001003.95%\frac{289,000}{7,308,000} \times 100 \approx 3.95\%7,308,000289,0001003.95%.

Verification with PSP Guidelines: The PSP Study Guide emphasizes accuracy in percentage-based cost contributions as a critical analysis tool in project cost management (Ref: PSP Study Guide, Chapter 1B: Cost Breakdown Structure).

Get access to all 216 verified questions with detailed answers.

Unlock All AACE-PSP Questions

Frequently Asked Questions

Candidates must have a minimum of 4,000 hours of professional planning and scheduling experience within the last 10 years, or 2,000 hours if they hold an AACE certification or a related bachelor's degree. Additionally, applicants must agree to adhere to AACE's Code of Ethics and Professional Conduct.

The PSP exam is 3 hours long and consists of 80 multiple-choice questions covering planning and scheduling principles. A score of 70% or higher is typically required to pass the examination.

The exam covers key areas including project planning fundamentals, work breakdown structures, scheduling techniques, resource management, risk and contingency planning, and schedule analysis and control. It also includes questions on project controls integration and stakeholder communication within the planning and scheduling context.

As of recent years, the exam fee is typically around $300-$400 for AACE members and higher for non-members, though prices may vary. Candidates can generally attempt the exam multiple times, with reasonable waiting periods between failed attempts as determined by AACE.

AACE recommends studying the official PSP Body of Knowledge document and related planning and scheduling references. Many candidates also utilize exam prep courses, study guides, practice tests, and networking with other planning and scheduling professionals to prepare for the certification.
Exam Details
  • Exam CodeAACE-PSP
  • VendorAACE International
  • Total Questions216
  • LanguageEnglish
  • Last UpdatedSep 2, 2026
4.9/5

Pass AACE-PSP First Time

Get all 216 exam questions with verified answers and 90-day free updates.

Buy Now & Pass
  • PDF + Practice Test Bundle
  • 90-Day Free Updates
  • 100% Money-Back Guarantee
  • Instant Download
  • 24/7 Customer Support
99% Pass Rate Trusted by 50,000+ IT professionals