C_TS412_2021 Exam Questions & Answers
SAP Certified Associate - SAP S/4HANA Project Systems • SAP
100% money-back guarantee
Sample C_TS412_2021 Questions
Practice with real exam-style questions, each with the verified correct answer and explanation.
You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing
reservation?
Note: There are 2 correct answers to this question
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set
of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
Get access to all 110 verified questions with detailed answers.
Unlock All C_TS412_2021 Questions