PMI-RMP Exam Questions & Answers
PMI Risk Management Professional • PMI
100% money-back guarantee
Sample PMI-RMP Questions
Practice with real exam-style questions, each with the verified correct answer and explanation.
A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.
What should the risk manager advise the project team?
In situations where available time and funds are insufficient to address all identified risks, it's imperative to prioritize risks based on their potential impact on the project. Focusing on high-impact risks ensures that the most critical threats to project success are managed effectively within the constraints. This approach involves conducting a thorough risk assessment to categorize risks by their severity and likelihood, allowing the project team to allocate resources strategically. By concentrating on high-impact risks, the team can develop contingency plans that safeguard the project's primary objectives, even if lower-impact risks cannot be fully mitigated due to resource limitations.
PMI Risk Management Study Guide Reference:
The PMI-RMP Exam Preparation Study Guide emphasizes the importance of prioritizing risks, stating that 'project teams often face constraints in resources, making it essential to focus on risks that pose the greatest threat to project objectives.'
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?
According to the PMI Risk Management Professional (PMI-RMP) Handbook1, one of the domains of the PMI-RMP exam isRisk Monitoring and Reporting, which involves tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating risk process effectiveness throughout the project1. The risk manager of the related project should have reformed the risk monitoring and closing process properly to ensure that the contingency budget is only used for the intended risks and not for other purposes.The risk manager should have also communicated the status and outcomes of the risk activities to the relevant stakeholders, such as the functional manager and the CEO, to avoid any confusion or conflict over the budget allocation1.Reference:1: PMI Risk Management Professional (PMI-RMP) Handbook, page 6.
The risk manager should have ensured a more accurate project work plan and budget to prevent the functional manager from requesting to use the project's contingency budget. A well-planned budget would have avoided the shortage in the functional manager's department budget.
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
The project manager should have updated the project schedule by adding risk owner implementation tasks. This would have ensured that the planned risk responses were implemented in a timely manner and tracked as part of the project schedule. This would also have allowed the project manager to monitor the progress of risk response implementation and take corrective action if necessary.
According to the PMI-RMP Exam Content Outline and Specifications1, one of the tasks under Domain 4: Risk Monitoring and Reporting is to ''update project schedule, budget, and risk register with risk response outcomes''. This implies that the project manager should have added the risk owner implementation tasks to the project schedule, so that they can be tracked and monitored. By doing so, the project manager could have ensured that the planned risk responses were executed as intended, and that the opportunities were not missed.Reference:PMI-RMP Exam Content Outline and Specifications, page 10.
In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.
In implementing this plan, which response should the risk manager use?
The appropriate risk response for an opportunity where the project team plans to assign more resources to ensure the company receives an incentive payment for early completion is to 'Exploit.' Exploiting a risk means taking action to ensure that the opportunity is realized, particularly when it is an opportunity with a positive impact that the project team wants to guarantee. In this case, the opportunity to complete the project early and receive an incentive payment aligns with the definition of an 'Exploit' response, as it is an active approach to maximize the benefits from the opportunity.
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?
The project manager should monitor and control secondary and residual risks in the risk register. This will ensure that any new risks identified during the implementation of the risk response plan are captured and managed effectively. Monitoring and controlling risks is a continuous process that helps in identifying, analyzing, and planning for new risks as well as updating the risk register as needed.
According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline, one of the tasks under the domain of Risk Response Planning is to ''identify and assess the effectiveness of alternative strategies to reduce threats or enhance opportunities, such as mitigation, transference, avoidance, and acceptance''1. This implies that the project manager should also consider the potential secondary or residual risks that may arise from implementing the chosen risk response strategy.Secondary risks are new risks that are created as a direct result of implementing a risk response, while residual risks are those that remain after the risk response has been executed2. Both types of risks should be identified and assessed for their impact and probability, and added to the risk register for further monitoring and control. Therefore, the correct answer is A.
Get access to all 289 verified questions with detailed answers.
Unlock All PMI-RMP Questions