You are the project manager for your organization. You have worked with the project team to create
the project scope statement. The key stakeholders have signed off on the project scope and they are
eager for you and the project team to begin creating the deliverables identified within the project
scope. What process must you and the project team complete next in this scenario?
Once the project scope statement has been approved, the project manager and the
project team should decompose the project scope
statement into the WBS.
Answer option A is incorrect. Before the activity list may be created, the WBS is needed. The activity
list is based on the work packages
identified in the WBS.
Answer option C is incorrect. Creating the risk assessment for the project is part of project planning,
but it is not the most appropriate process
to complete at this time.
Answer option D is incorrect. Determining the project budget is the process of aggregating the
estimated costs of individual activities or work
packages to establish an authorized cost baseline. Determining the project budget is a part of project
cost management.
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?
Contingency reserves are estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events. These events are 'known unknowns' and are part of the project scope and cost baselines. The contingency reserve is calculated by multiplying the probability and the impact for the risk event value for each risk event. The sum of the risk events equals the contingency reserve for the project. Note that Risk D is a positive risk amount. Answer option C is incorrect. This value is the sum of the risk events if you did not include Risk D as a positive risk value. Answer option A is incorrect. This is a sum of the risk event. Answer option B is incorrect. This is a sum of the risk events without including Risk D as a positive risk event.
You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts
related to the outputs of the control
schedule process. Which of the following is an output of the control schedule process?
Only change request is a valid answer. The five outputs of the control schedule process
are work performance measurements, organizational
process assets updates, change requests, the project management plan updates, and project
document updates.
Change requests are requests to expand or reduce the project scope, modify policies, processes,
plans, or procedures, modify costs or
budgets or revise schedules. These requests for a change can be direct or indirect, externally or
internally initiated, and legally or contractually
imposed or optional. A Project Manager needs to ensure that only formally documented requested
changes are processed and only approved
change requests are implemented.
Answer option D is incorrect. Activity resource requirement is not an output of the control schedule
process.
Answer option A is incorrect. The project schedule is not an output of the control schedule process.
Answer option B is incorrect. Lessons learned is not an output of the control schedule process.
You are the project manager of the MQQ project. Unfortunately, this project is not performing well
and you must do something to address the
problems in your project. Based on your planning for monitoring and controlling project
performance, you know that there are three outputs of
performance reporting. Which one of the following is the only output that is most appropriate for
this poorly performing project?
Change requests are an output of performance report, and allow the project manager
to address corrective actions and preventive actions to
help the project get back in alignment with performance baselines.
Answer option B is incorrect. While performance reports are an output of the performance
reporting, these reports do not specifically address
the problems in the project.
Answer option A is incorrect. Updating the organizational process assets is an important activity, but
it does not address the poor
performance directly.
Answer option C is incorrect. Performance re-baselining is not an output of performance reporting
so this choice is not valid.
Robert is the project manager for his organization. Management has asked Robert to provide them
with the metric he uses to measure deliverables status, costs incurred, and especially how he
measures the schedule progress for schedule adherence. What project component could Robert
provide for management?
Work performance measurements are metrics that are defined to collect performance
and progress of the project. Typical metrics are
deliverables, schedule, and costs, though additional metrics, such as quality, can be added.
Work performance measurements are created from the work performance information. WPMs are
an output of Control schedule, Control cost,
and Control scope processes, which are monitoring and controlling processes. WPMs consist of
planned versus actual performance indicators
with respect to scope, schedule, and cost. They are documented and communicated to the
stakeholders and are used to make project activity
metrics, such as the following:
Planned vs. Actual Technical performance and Scope performance
Planned vs. Actual Schedule performance
Planned vs. Actual Cost performance
Answer option D is incorrect. The project management plan is too broad and is not the best choice.
Answer option B is incorrect. The cost management plan and the project schedule would not provide
all the information that management has
requested.
Answer option A is incorrect. The milestone list does not include performance metrics.