Q1 MultipleChoice

You are the project manager for your organization. You have worked with the project team to create

the project scope statement. The key stakeholders have signed off on the project scope and they are

eager for you and the project team to begin creating the deliverables identified within the project

scope. What process must you and the project team complete next in this scenario?

Correct Answer: B
Explanation:

Once the project scope statement has been approved, the project manager and the

project team should decompose the project scope

statement into the WBS.

Answer option A is incorrect. Before the activity list may be created, the WBS is needed. The activity

list is based on the work packages

identified in the WBS.

Answer option C is incorrect. Creating the risk assessment for the project is part of project planning,

but it is not the most appropriate process

to complete at this time.

Answer option D is incorrect. Determining the project budget is the process of aggregating the

estimated costs of individual activities or work

packages to establish an authorized cost baseline. Determining the project budget is a part of project

cost management.

Q2 MultipleChoice

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

Correct Answer: D
Explanation:

Contingency reserves are estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events. These events are 'known unknowns' and are part of the project scope and cost baselines. The contingency reserve is calculated by multiplying the probability and the impact for the risk event value for each risk event. The sum of the risk events equals the contingency reserve for the project. Note that Risk D is a positive risk amount. Answer option C is incorrect. This value is the sum of the risk events if you did not include Risk D as a positive risk value. Answer option A is incorrect. This is a sum of the risk event. Answer option B is incorrect. This is a sum of the risk events without including Risk D as a positive risk event.

Q3 MultipleChoice

You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts

related to the outputs of the control

schedule process. Which of the following is an output of the control schedule process?

Correct Answer: C
Explanation:

Only change request is a valid answer. The five outputs of the control schedule process

are work performance measurements, organizational

process assets updates, change requests, the project management plan updates, and project

document updates.

Change requests are requests to expand or reduce the project scope, modify policies, processes,

plans, or procedures, modify costs or

budgets or revise schedules. These requests for a change can be direct or indirect, externally or

internally initiated, and legally or contractually

imposed or optional. A Project Manager needs to ensure that only formally documented requested

changes are processed and only approved

change requests are implemented.

Answer option D is incorrect. Activity resource requirement is not an output of the control schedule

process.

Answer option A is incorrect. The project schedule is not an output of the control schedule process.

Answer option B is incorrect. Lessons learned is not an output of the control schedule process.

Q4 MultipleChoice

You are the project manager of the MQQ project. Unfortunately, this project is not performing well

and you must do something to address the

problems in your project. Based on your planning for monitoring and controlling project

performance, you know that there are three outputs of

performance reporting. Which one of the following is the only output that is most appropriate for

this poorly performing project?

Correct Answer: D
Explanation:

Change requests are an output of performance report, and allow the project manager

to address corrective actions and preventive actions to

help the project get back in alignment with performance baselines.

Answer option B is incorrect. While performance reports are an output of the performance

reporting, these reports do not specifically address

the problems in the project.

Answer option A is incorrect. Updating the organizational process assets is an important activity, but

it does not address the poor

performance directly.

Answer option C is incorrect. Performance re-baselining is not an output of performance reporting

so this choice is not valid.

Q5 MultipleChoice

Robert is the project manager for his organization. Management has asked Robert to provide them

with the metric he uses to measure deliverables status, costs incurred, and especially how he

measures the schedule progress for schedule adherence. What project component could Robert

provide for management?

Correct Answer: C
Explanation:

Work performance measurements are metrics that are defined to collect performance

and progress of the project. Typical metrics are

deliverables, schedule, and costs, though additional metrics, such as quality, can be added.

Work performance measurements are created from the work performance information. WPMs are

an output of Control schedule, Control cost,

and Control scope processes, which are monitoring and controlling processes. WPMs consist of

planned versus actual performance indicators

with respect to scope, schedule, and cost. They are documented and communicated to the

stakeholders and are used to make project activity

metrics, such as the following:

Planned vs. Actual Technical performance and Scope performance

Planned vs. Actual Schedule performance

Planned vs. Actual Cost performance

Answer option D is incorrect. The project management plan is too broad and is not the best choice.

Answer option B is incorrect. The cost management plan and the project schedule would not provide

all the information that management has

requested.

Answer option A is incorrect. The milestone list does not include performance metrics.

Get access to all 326 verified questions with detailed answers.

Unlock All PMI-SP Questions

Frequently Asked Questions

To be eligible for the PMI-SP exam, you must have at least 3,500 hours of professional experience in scheduling within the last 8 years, and 30 contact hours of formal education in scheduling. Additionally, you must hold a current PMI membership and agree to abide by the PMI Code of Ethics and Professional Conduct.

The PMI-SP exam consists of 200 multiple-choice questions that must be completed within 4 hours. The exam is designed to test your knowledge of scheduling principles, practices, and competencies across various project management contexts.

The PMI-SP exam covers five main domains: scheduling fundamentals, scheduling planning, scheduling development, schedule monitoring and controlling, and resource optimization. These domains encompass topics such as schedule network analysis, critical path method, resource leveling, and schedule performance management.

PMI does not publish the exact passing score for the PMI-SP exam, as it uses a scaled scoring method that adjusts for exam difficulty. However, you generally need to answer approximately 70-75% of questions correctly to pass, which translates to roughly 140-150 correct answers out of 200 questions.

The PMI-SP certification is valid for 3 years from the date of certification. To renew your certification, you must earn 60 Professional Development Units (PDUs) during the 3-year period, maintain active PMI membership, and comply with the PMI Code of Ethics and Professional Conduct.
Exam Details
  • Exam CodePMI-SP
  • VendorPMI
  • Total Questions326
  • Duration120 min
  • LanguageEnglish
  • Last UpdatedSep 4, 2026
4.9/5

Pass PMI-SP First Time

Get all 326 exam questions with verified answers and 90-day free updates.

Buy Now & Pass
  • PDF + Practice Test Bundle
  • 90-Day Free Updates
  • 100% Money-Back Guarantee
  • Instant Download
  • 24/7 Customer Support
99% Pass Rate Trusted by 50,000+ IT professionals